Wind farm built in six months
|
The 80 wind turbines was erected in the summer
months of 2002. The building project were subject to the tough conditions in the North
Sea, so planning and careful preparation were essential. The turbines was
installed in six phases, but the entire project obviously depended on the actual
weather conditions.
|
|
Manufacturing and installation - overall time schedule
Time Schedule
Site Works - a time schedule in six phases
Click on the schedule to view it in full size.

|