|
|
Offshore wind turbines in an
energy policy perspective
The Danish Government’s energy action plan "Energi
21" targets a reduction in CO2 emissions by 50% by
2030 (as compared to 1988). Wind power is the most economical means of
reducing the emission of CO2 as far as the production of
electricity is concerned. As the erection of additional land-based wind
farms would create unacceptable concentrations of wind turbines, the
target is to establish 4000 MW at sea by 2030, as they will be less of a
nuisance there.

Siting and visualisation
Since 1983, several studies concerning the siting of wind turbines
at sea have been completed. And in 1994, the builders began gathering
insight on the various interests of officials and others, interests
which would have to be taken into consideration in the establishment of
an actual offshore wind farm. The next step was to identify appropriate
locations for carrying out the demonstration project. This phase
culminated in two central analyses: a landscape project designed to shed
light on the impact an offshore wind power installation would have on
the nearby coastal landscape, and a survey project designed to register
all known interested parties. Based on the findings of these projects,
the builders arrived at four main areas for siting offshore wind farms.
These included an area near Horns Rev and a larger area south of the
island of Læsø in Skagerrak.

Plan of action
I 1997, a plan of action dubbed the "Action Plan for Offshore
Windfarms in Danish Waters" was conceived. This report concluded
that large-scale offshore wind farms are interesting, technically and
economically as well as environmentally. The recommendation? Prepare for
the construction of "stage-one demonstration projects!"
Demonstration installation
In 1998, Danish power suppliers were challenged to erect five offshore
wind farms which could produce a total of approx. 150 MW. Two of those
are located west of the Great Belt – one at Horns Rev and the other
south of Læsø.
Preliminary permission
In mid-1999, the power suppliers received the preliminary go-ahead to
begin the construction of four offshore wind farms: Horns Rev, Læsø,
Omø Stålgrunde, and Rødsand. The approvals were a sign that the
power suppliers could expect a definitive green light for the projects
unless the EIA (Environmental Impact Assessment) process turned up
unfavourable results. So the preliminary technical and environmental
studies could begin.
Adjustment in 2002
The Danish government cancelled the order given earlier to
the utilities for three Danish offshore wind farms, the construction of
which has not yet started. The cancellation involves the Læsø, Omø Stålgrunde
and Gedser Rev wind farms.
Builders
As regards the projects at Horns Rev, Elsam
is responsible for the actual wind farm – installing and maintaining
the turbines, the turbine foundations, the internal cabling, the
accompanying remote control unit, and auxiliary installations. Eltra is
the builder in charge of the installations designed to convey the power
ashore, that is, the offshore transformer substation, the sub-marine
cable leading to land and the onshore cable leading to the general
transmission grid.
Project Committee
Elsam established a Project Committee based on resources from Elsam
and Elsam Engineering. This committee gathered expertise in all aspects of the
field of wind power, from planning, engineering and environment to
the financial and operational aspects. Elsam
Engineering
A/S
is a subsidiary of Elsam.
|