|
Eltra's
substation in place
On
April 15 the barge carrying Eltra's substation arrived at the Port of
Esbjerg after an approximately 70-hour transport from Rotterdam. In
the Port of Esbjerg the great crane Asian Hercules was ready to hook
the 1,150-tonnes substation and transport it to the Horns Rev
construction site. The maximum capacity of the Asian Hercules is 3,200
tonnes!
Early
in the morning on April 16, at 5 am, the Asian Hercules set off for
the Horns Rev. The weather was perfect: sunny, no wind and almost a
totally calm sea. The conditions for the offshore installation
couldn't have been better!
After
having waited for the tides to shift so that the currents were
minimal, the lifting operations were initiated, which should place the
substation on its tripod foundation. At 2 pm, the substation was in
place in the right position and the Asian Hercules was able to
dismantle the hoisting devices and return to the Port of Esbjerg.
Now,
some work has to be done prior to the commissioning of the substation.
This work is also progressing well and the substation is now ready for
helicopter landings and take-offs. Now, all that is needed is the
final approval from the Danish Civil Aviation Administration.
Cable
pulling is expected to be initiated in the very near future. |