|
Read about:
|
All
80 wind turbines in operation
On 11. December at 14.00, the last of the 80 wind
turbines at Horns Rev was put into operation by specialists from
Vestas. This marked the conclusion of almost 4 months of hectic
activity, completing the installation work and testing the turbines.
The commissioning phase of the project was delayed
by approx. 1 month in relation to agreed schedule.
During this time, Vestas has had up to 50 fitters at
the rev, where the two crane-vessels from A2SEA, Ocean Hanne og Ocean
Addy, have functioned as hotel-ships. 4 – 5 chartered transfer boats
have transported the fitters around between the turbines, where they
have been fitting cables and testing the turbine’s mechanical and
electrical systems.
After commissioning, the turbines can be put into
normal operation, however experience shows that some minor faults and
alarms can arise during this phase. These must be rectified on the
turbines before full operation can be achieved. To date, the
production record from Horns Rev has been approx. 110 MW with 50-60
turbines in operation simultaneously.
The advanced remote control equipment is connected
to all the turbines in the park via fibre optic cables. So that,
Vestas og Elsam have via the remote control equipment, direct access
to the turbine controls and can from land respond to information and
operational data from the turbines.
There remains as yet some outstanding work and
repairs to be completed – primarily concerning the longevity of the
turbines. This work is expected to be completed in spring 2003.
Moreover, one or two of the blades on the park’s turbines were found
to be damaged by lightning during a thunder storm in the area, in the
autumn. Replacement blades are expected to be installed by the end of
December.
The turbines shall in accordance with the agreement
between Vestas and Elsam demonstrate a stabile operation for a
prearranged period of time. When all the turbines have completed this
trial operation – both singularly and in groups – the turbines can
finally be taken over and commercial operation can commence. This is
expected to occur at the start of 2003.
While Vestas has been working hard to finish the
installation and commissioning of the turbines, MT Højgaard has been
carrying out extra laying of stone as a security measure against
corrosion around the submarine cable casings where necessary.
Approximately 45.000 ton of this additional stone has been laid.
|
|

On 11. December at 14.00, the
last of the 80 wind turbines at Horns Rev was put into operation

Horns Rev - 80 Wind turbines - 160 MW.

The turbines shall demonstrate
a stabile operation for a prearranged period of time.
|
|
Maintenance
of the wind turbine park
The park is finally expected to be taken over at the
beginning of the new year, after which the task of servicing the
turbines can begin. Although, Vestas is responsible for the servicing
the park, and with active participation from Elsam. As a starting
point for this, a standard service team will be established,
consisting of employees from both Elsam and Vestas.
Initially, tasks to be carried out at the park are
expected to arise almost every day, however it is also expected that
the installation will be run in over the course of the first year.
After the running-in period, the number of visits required is expected
to be reduced to an average of every second day.
The standard mode of transport to the park will be
helicopter. Consequently, allowing access to the park regardless of
the adverse sea conditions which would otherwise prevent sailing in
the area for approximately one third of the year.
The first team of service technicians have just
completed the necessary education . Most of the education was related
to the installation, in which all participated, however in relation to
the service work, the service technicians shall attend a special
training program where they learn how to be hoisted down to the
turbines from a helicopter. 26 persons are currently trained to do
this. Besides the service personnel, workers from the project
departments in Elsam’s subsidiary Tech-wise have also completed the
education.
Besides the service technicians, who handle the
daily work out at the wind turbine park, a staff has been assembled,
who shall manage and support the service work. This involves amongst
others, tasks relating to the coordination of transport by boat and
helicopter, monitoring of the operational status of the turbines and
registration of the work carried out.
|

The standard mode of transport to the
park will be helicopter.

26 persons are currently trained to to be
hoisted down to the turbines from a helicopter.
|
|
Experiences
Naturally, in the course of such a large and
innovative project as the Horns Rev-project, an extensive list of
experiences and valuable knowledge are bound to be gained. We
asked Elsam’s project leader on Horns Rev-project, Jens W.
Bonefeld, to give a brief introduction to the most important of them.
By
Jens W. Bonefeld
As the Horns Rev project is about to enter its final
phase, it provides an opportunity to pause and reflect upon the
experiences gained.
The planning for such an innovative project has been
very important. The project has benefited from the fact that parallel
to the required environmental surveys there had been sufficient time
to gather the prerequisites for climatic and soil conditions. This has
provided a good basis to undertake preliminary engineering evaluations
of the construction, implementation and operation of the park.
Moreover, this has provided a platform for defining
some of the implementation and contractual frameworks for the
contractors and suppliers. Their contribution to the process has led
to the overall success of establishing the park. Elsam’s suppliers
and contractors have reacted well to this good basis by working
whole-heartedly towards the success of the project. The suppliers and
contractors have experienced that the project has placed great demands
on the planning of logistics and equipment selection and that it has
also been necessary to adjust methods and equipment concepts. Having
said that, it can be noted in contrast that a project with 80
identical units has enjoyed a lot of repetition and that the learning
from this has been especially impressive over the summer
Elsam chose to coordinate the work by drawing up
independent contracts for the individual project groups concerned (multi-contract
principal). This meant that following up on the time schedule and the
technical and implementation interfaces was critical. Experience has
shown that this demands great vigilance and care to succeed.
Seen from Elsam’s side, the task of coordinating
the work at Horns rev has also been immense, concerning safety,
traffic control and diving work. In this area, much valuable
experience was gained which can benefit other projects. In this
respect, the collaboration with the public authorities has played a
great role – this type of project also involves new aspects for them.
The Horns Rev project has opened up a new business
area within the energy industry and the emergence of opportunities for
continual development. Elsam as an energy producer will pursue these
opportunities and is already involved in similar projects around
Europe. The suppliers and contractors will similarly pursue these
opportunities. The wind turbine manufacturers are seeking to increase
the size of their turbines and similarly adapting them to operating
conditions. Contractors are also looking at possible investments in
equipment which could be adapted to suit special types of projects.
However one must not forget, that there still
remains a great challenge in the operation and maintenance of the park
for many years to come, as long as the production is high and the
maintenance costs low. This chapter is just beginning.
|
Elsams project
leader on Horns Rev-project
Jens W.
Bonefeld.
|
|
Important
events
of the Horns Rev Project
|
|
2
MW test wind turbine in Tjæreborg once again in operation
On Monday 4. November at approx.
9.00 a.m. the new 2 MW offshore test wind turbine i Tjæreborg was
damaged. The wind turbine is a prototype of the 80 wind
turbines, which Elsam has erected at Horns Rev. After the incident
Vestas carried out a through investigation into the cause of the
damage. They concluded that the fault occurred in the turbine’s
safety system as a result of a human error related to work carried out
on the turbine on the 24. October 2002. The fault was restricted to
this single wind turbine. Shortly after the incident, the turbine was
fitted with new blades and is now back in operation.
|
|
|
3
MW Vestas turbine mounted on a “bucket foundation” at
Fredrikshavn
Elsam has just erected the largest
wind turbine in Denmark - a Vestas V90/3 MW turbine on a “bucket
foundation” off the harbour of Frederikshavn. The turbine is a
further development of the 2 MW offshore turbines Elsam has employed
at Horns Rev. The wind turbine has a rotor diameter of 90 M and an
overall height of 125 M. Altogether there are 4 offshore
turbines on the site, giving a total output of 10,6 MW. The turbines
are supplied by Bonus, Vestas and Nordex. The other three
turbines are erected out from the harbour in Frederikshavn, on a
traditional foundation and are expected to be in operation by June
2003.
|

3 MW Vestas turbine mounted on a
“bucket foundation” at Fredrikshavn
|
|
Aalborg East
On a
site by Aalborg østhavn, Elsam has just erected the latest offshore
turbine from NEG Micon. The turbine is a NM92/2750 type, which is NEG
Micon’s largest model to date. The 2,75 MW turbine has a total
height of 115 M and a rotor diameter of 92 M and is a newly developed
offshore model.
|

Elsams 2.75 MW
offshore
turbine under erection by Aalborg Østhavn
|
|
Last newsletter
This
is the last regular newsletter to be sent in connection with the Horns
Rev project. In the near future, the park will go into commercial
operation and pass over to Elsam’s departments for operation and
maintenance of wind turbines.
However,
a constant registration of the park’s environmental significance
will still continue. We will continue to make the ongoing reports
available here on the project’s home
page. Moreover, we cannot rule
out the need for further newsletters concerning environmental surveys
pertaining to the project, at a later date.
|
|
| Issued
newsletters
|
|
|
Elsam A/S
Overgade 45
DK-7000 Fredericia
Phone: +45 76222000
Fax: +45 76221962
www.elsam.com
|
|