|
Site management
The overall site management and site
supervision is currently being organised. The main positions have
been filled and we are now doing our utmost to fill the last
positions, both from Elsam's and Tech-wise's current staff and from
external sources.
The site management and supervision
will have their offices in Esbjergværket's premises at
Vestkraftgade 1, 6700 Esbjerg. From early March the offices will be
ready and at about the same time the actual supervision has to start
at the construction site at Port of Esbjerg.
Traffic control
A Traffic Control Unit will be established. Their job will be to
control safety at sea and to coordinate the many different vessels
that will call at the Horns Rev offshore construction site. The
Traffic Control Unit will supervise the positions of all vessels and
will log all persons, who are physically present between the Port of
Esbjerg and between or at the temporary construction site area at
Horns Rev during the entire construction period.
Diving control
All diving activities in connection with the construction of the
Horns Rev wind farm will be coordinated and monitored by Elsam.
Diving operations may be of a high risk and consequently, much focus
will be put on planning, monitoring and reporting this type of work.
Diving operations will primarily be carried out in connection with
the pulling of the sea cables but other installation activities also
require the assistance of professional divers in the North Sea which
are difficult waters with strong currents and frequently changing
sea conditions. The diving control unit is being established at
present.
Marking by
buoys of temporary offshore construction area
Marking of the construction area has
been reported to the Royal Danish Administration of Navigation and
Hydrography (Farvandsvæsenet). Further information may be found at
their homepage under Notices to Mariners in the menu Publications:
www.fomfrv.dk
|
|

|
|
|
|
Storing of foundation
parts at the Port of Esbjerg
Foundation parts are being shipped out
of Antwerp. On February 13, 2000, the first shipment arrived of piles
and transition pieces for MTH's storage area at the Port of Esbjerg.
The coaster hired for the purpose can only transport two piles and two
transitions pieces on deck and in the coaster's cargo room, a total of
four complete foundations.
[Coaster with two transition pieces on
deck. The piles have been unloaded]
Piles and transition pieces are
unloaded by means of two large crawler cranes that bring the parts to
the storage area next to the berths. Here, sand and gravel heaps have
been arranged in 2´ 2 rows on which the piles are placed.
|

Unloading of pile

Unloading of transition piece
|
| Storing
of first turbine towers in Esbjerg
The production of towers, nacelles and
rotors is well under way at Vestas' factories.
The towers are produced at the
facilities in Varde and are then transported to the painter's, Gardit,
in Esbjerg for abrasive blasting, painting and treatment of internal
surfaces including fitting of ladders, platforms, electrical
installations and lighting. Each tower section is subsequently placed
at temporary storage facilities at Gardit's before being transported
to Vestas' pre-assembly area at the Port of Esbjerg (Traffic).
|

Five towers are ready at the temporary
storage facilities at Gardit's.
|
|
Status on the testing of A2SEA's
first crane vessel
As mentioned in our January
Newsletter, A2SEA, a sub-supplier of Vestas' that are supplying
and operating the two crane vessels for sea transport and lifting of
the wind turbines, are currently testing the first crane vessel, Ocean
Hanne at the Horns Rev site.
From the Port of Esbjerg the vessel has
conducted a number of testing sessions for positioning of the vessel,
jacking-up the legs and simulating on-site lifting jobs of turbine
components under various weather conditions.
The tests will continue for some time
but there is a break in early March during which the vessel will be
fitted with hotel containers etc. This will be done in Esbjerg.
The second crane vessel, Ocean Addy,
has left the yard at Frederikshavn to have the same fitting jobs done
as Ocean Hanne.
|

A beautiful
day at Horns Rev
|
|
Foundations for Horns Rev - Manufacturing
of piles
MT Højgaard work with two Dutch
sub-suppliers, who produce and process the steel parts for the Horns
Rev turbine foundations. One of these contractor, SIF Group, produce
the base material for the piles and transition pieces whereas the
other contractor, Rheden Steel, fits the piles and transition pieces
with steel equipment such as boat landing arrangement, J-tube sleeves,
platforms, etc. Rheden Steel is also responsible for the surface
treatment of the pieces.
For this job Rheden Steel has rented
some facilities at a former shipyard in Antwerp where there is ample
space and cranes for storing and handling large and heavy components.
The access to the river Shelde from the shipyard is a great advantage.
The foundations are easily shipped to Esbjerg from here.
|

Transition piece ready for crane handling

Components after paint treatment
|
| Helicopter
transportation
Elsam has signed a contract with
Uni-Fly A/S for helicopter transportation to the offshore wind farm at
Horns Rev. Throughout the year, Uni-Fly A/S places a helicopter at
Elsam's disposal to fly maintenance staff to wind turbines with
operating failures.
The wind conditions at Horns Rev are
good, which however means that sailing may be difficult due to wave
conditions, especially during winter. That is why it has been decided
to fly maintenance staff to the wind farm, hoist the staff down on to
the turbines and pick them up again in the same way as in rescue
operations after they have done the job. The method is widely used
abroad, for instance in the Channel where the hoisting method is used
for transporting pilots from ship to ship.
|

Elsam has signed a contract with Uni-Fly A/S for helicopter
transportation
|
|
Measurements
at Horns Rev - an important design parameter
Since spring 1999 a number of
measurement systems have been installed at Horns Rev measuring wind,
wave and current conditions as well as water depths.
The systems are full automatic and are
currently sending results ashore both via GSM communication and via a
special-purpose radio transmitter. The systems are primarily operated
by solar power. An exposed device measuring the currents is however
operated by a built-in battery that is changed at intervals of a few
months.
Despite the harsh climate at the reef,
the systems have been highly reliable and since 1999 we have gathered
quite a lot of data on the conditions in which the wind farm will
operate.
Knowledge of the wind conditions is of
course crucial when it comes to calculating the actual production of
the turbines and the turbine design will also be have to be adapted
to, for instance, how strong the wind gusts are and to the character
of the wind (turbulence).
The wave conditions also depend on the
wind, both the strength and direction of the wind and also on currents
and water depths.
All these data are used in the planning
of how and when maintenance is to be carried out. Different means of
transportation are suitable for different wind and wave conditions and
special effort will be put into optimising the choice of the right
means of transportation. The choice will be based on the probability
of being able to operate under the given conditions against an
estimated loss of production due to non-operation of the turbine and
on the amount of money to be paid for the waiting time of the
maintenance staff.
All these considerations have resulted
in the choice of a helicopter as the main means of transportation to
the turbines and boat/zodiac has been chosen as number one
alternative. Since this is the first time such a big offshore wind
farm is built we have no previous experience to draw upon when it
comes to transportation. That is why we also work with the alternative
of a larger boat calling the turbines directly.
Based on the wind and wave measurements
it has been calculated which types of boats would be best suited and
how power it would take to keep them in position at the turbines. The
turbine foundations are consequently prepared for installation of boat
landing arrangements if it should prove necessary to change to boat as
primary means of transportation.
|

Since spring 1999 a number of
measurement systems have been installed at Horns Rev measuring wind,
wave and current conditions as well as water depths.
|
| Issued
newsletters
|
|