| Elsam
is ready to compete for offshore projects in a completely
liberalised market
Elsam is still very interested in
building offshore wind farms even though the newly-elected Danish
Government has decided to stop the development of three of five
scheduled offshore demonstration wind farms. In an interview with
Ritzau on 23 January 2002, Elsam's CEO Mr Høstgaard-Jensen says
Elsam is ready to compete for the projects should they be put out to
tender.
Elsam is the owner of the world's so
far largest offshore wind farm that will be built at Horns Rev in
the North Sea this summer. Elsam was also ordered by the former
government to build the offshore wind farm south of the island of
Læsø. This project, however, and the offshore projects at Omø
Stålgrunde and Gedser Rev have been dealt the Government's
deathblow.
"The consequences of the new
Government's decision are still not clear to us but it seems that
Elsam will be relieved of the order to build the offshore wind farm
south of Læsø", says
Mr Høstgaard-Jensen.
For some time Elsam has worked on a
study mapping the environmental impacts of a wind farm at Læsø. Mr
Høstgaard-Jensen expects the Læsø project be put out to tender
and it will only be natural for Elsam to tender for the project.
"Environmental-friendly energy
plants are of our main interest and the production of electricity at
such plants is our core business area. If the construction of these
farms is to take place in a liberalised market, we shall tender for
them even if there are several bidders",
says Mr Høstgaard-Jensen.
|
|

Mr Peter Høstgaard-Jensen
Chief Executive Officer
Elsam A/S.
|
|
|
| A2SEA's
first crane vessel is being tested
A2SEA is currently testing the first of
the vessels, the "Ocean Hanne". A2SEA is a sub-supplier of
Vestas' which is to supply and operate the two crane vessels for sea
transport and lifting jobs in connection with the installation of the
turbines at Horns Rev,.
"Ocean Hanne" which departed
from Ørskov Shipyard in Frederikshavn just before the Christmas
holidays, was tested in the Bay of Ålbæk around the turning of the
year. Turbine lifts were simulated: the vessel was jacked up on
its four legs and the main crane lifted
a load, already on board the vessel. See below.
The results of the tests showed that
under the wind and wave conditions on the day of the test, the vessel
was very stable and the lifting job was carried out without problems.
"Ocean Hanne" continued to the Port of Esbjerg to make a
series of tests at Horns Rev as well.
It soon became clear that the vessel's
winch was not sufficiently powerful to secure the vessel's position
under the more harsh conditions in the North Sea. Nevertheless, a
number of tests were carried out just like in the Bay of Ålbæk and
the vessel's required lifting capacity seemed acceptable. At present,
"Ocean Hanne" is at the Port of Esbjerg to solve the winch
problems. Once these problems are solved, the thorough tests at Horns
Rev will continue.
|

Ocean Hanne was tested in the Bay of
Ålbæk around the turning of the year. Turbine lifts were simulated
|
|
Pile driving vessel
The main contractor for the foundations,
MT Højgaard, has joined forces with Mammoet, a Dutch company, for the
job of constructing the foundations on site. For this purpose, Mammoet
is currently building a completely new vessel that - by means of four
legs - can lift itself out of the water, a so-called jack-up vessel.
To be able to operate under extreme
weather conditions at Horns Rev it has proven necessary to make the
legs very robust. The picture shows one section of a total of three
sections, which form one jack-up leg. The legs will be approx. 33 m
long and the cross-section 3.5 ´ 3.50m. Each leg will have a
so-called spud can which is 8 ´ 8m and weighs approx. 70 tonnes.
In principle, the vessel's hull - which
is also the jack-up vessel's work platform - is a rectangular box 100m
long, 33m wide and 7m high. In the picture a section of the hull is
being loaded onto a barge that will transport the hull section to the
main shipyard where the hull will be assembled (other sections and the
jack-up legs). Section size: 16.5m wide, 7m high and 8 m long.
When ready for operation, the jack-up
vessel will carry ten monopiles (approx. 1,500 tonnes) and other
equipment for driving the turbine foundation piles.
|

Manufacturing of one section for a jack-up leg

Section of the hull, ready for shipment from sub-supplier's to
Mammoet's
|
| Satellite
transmitters on the first seals
In connection with the environmental
monitoring programme initiated for the Horns Rev project it was
decided to follow the migration of seals in the area to examine
whether the construction of the wind farm may have an undesired impact
on seals' lives in the Wadden Sea.
During a kick-off meeting led by Marine
Biologist Svend Tougaard, held at Fanoe Rescue Station, 15 men were
instructed in the demanding work of capturing the seals. What makes it
so hard and demanding is that the seals are not so curious that they
swim into the nets voluntarily. In fact, they fight aggressively!
When the men arrived at the site, the
seals were lying on a sand bar on the northern tip of the Island of
Fanø. Half the group of men rushed to the bar in a fast rescue boat.
It was a beautiful winter morning with temperatures around the
freezing point and it was quite a cold experience. Within a few
minutes all seals were captured in a net and put in individual nets
(bags) in which they couldn't move but weren't
hurt either.
The furs of the seals were then brushed
thoroughly. The furs were extremely greasy - as are the hairs of all
those who do not wash regularly - and it was necessary to clean and
dry the furs to be able to attach the transmitters correctly.
[photo: seals are not tamed animals and
they defend themselves vigorously when approached by humans]
After a couple of hours of struggling
with marking the seals they were released one by one, and watching
their behaviour was very exiting. The first seal released rushed to
the sea and swam off. Another one moved slowly towards the sea, turned
his head and glanced at the men as if to check out his watchmen.
Later on, the positions of the seals
were registered on the computer and at present at least one of the
seals has already been in the wind farm area to check it out.

Picture in large
format
The migration of the ten seals will be
monitored from now till May where the transmitters will no longer send
out signals due to exhausted batteries. The transmitters will fall off
in the autumn when the seals shed their fur.
|

The first four seals (of a total of ten) were fitted with
transmitters at the first "seal hunt" in early January 2002.

It was necessary to clean and dry the
furs to be able to attach the transmitters correctly.

The
transmitter is glued to the fur

Seals are not tamed animals and they
defend themselves vigorously when approached by humans.
|
| Testing
of J-tubes
All turbines are fitted with cable
tubes, also known as J-tubes. The purpose of the tubes is to protect
and keep the cable in position at the transition piece between the
turbine foundation and the seabed in which the cable is washed.
Primarily due to installation aspects
the foundation supplier has wished to change the initial design of the
J-tube from a design based on steel to a design using plastics (PEH).
To verify that the new J-tubes were suitable for use in the harsh
marine environment at Horns Rev a series of design tests were carried
through. Firstly, these tests were aimed at verifying the tubes'
ability to resist the pressure from the erosion protection of the
foundations and, in addition, the ability to resist possible collision
with drifting objects.
Later, tests were carried out on an
installed J-tube to verify whether the structure was stable during
pulling of the real cable. The first test was executed by pulling a
steel wire through the J-tube. The tractive effort had been
pre-defined by the cable supplier.
To conclude the test series, a final
full-scale test was made. All tests had satisfactory results and a
solution was chosen for the J-tubes.
|

Compression test of J-tubes

Full-scale test.
|
| Marking
lights in Tjæreborg
Two red marking lights have now been
installed on the Horns Rev prototype turbine erected in Tjæreborg (see
the Horns Rev Newsletter of December 2001).
The lights have been installed to carry
out thorough tests; not least the rather advanced candela control. The
Danish Civil Aviation Administration make test flights in the area
under different weather conditions to test the marking lights.
The lights are not automatic and will
be removed after the necessary tests. |

Marking lights have now been installed
on the Horns Rev prototype turbine erected in Tjæreborg.
|
|
Eltra's substation,
status
Our Newsletter
of November 2001 describes the problems with the driving of
foundation piles for the substation. There has been no news to report
since then. A schedule will be drawn in the near future for the
driving of the remaining piles.
The platform is under construction at
HBG Steel Structures in Holland, the main contractor. In the coming
two months they will be very busy preparing for the start-up of the
technical installations in March.
|

The main steel structure for the platform topside during
installation. The heli-platform and facade panels will be fitted to
the substation while it is still at the workshop.

The Alstom 170 kV wind farm transformer
unit unloaded at HBG's berths.
|
| Issued
newsletters |
|