|
Cable
pulling and connecting of sea cable
The activities at
the Horns Rev construction site are now in highest gear and the
contractors are working intensively with the foundation pile driving
and the turbine installation. And the internal cable pulling for the
wind farm has been initiated. Late May, Nexan, the cable supplier,
started pulling the cables, which connect the turbines and the
substation.
Cable pulling and
connecting are scheduled to follow the turbine installation to avoid
damaging of the cables.
The cables are
trenched at a depth of 1-2 meters in the seabed by a cable-laying
vessel. At the turbines the cable is pulled into a protecting J-tube
and guided to the turbine where it is connected to the turbine's
high-voltage high-voltage system. At the seabed, divers make sure
that the cable enters the J-tube correctly. At the substation, the
cable is guided into the J-tube and connected to the transformer via
a 34-kV switchgear.
The turbines are grouped in
five radial configurations of 16 turbines each. 34 kV voltage
applies from the turbines to the substation's transformer. After the
transformer, the voltage is 150 kV.
The cable work includes the
submersion of the cables, which connect the five turbine groups to
the transformer at the substation as well as the submersion of the
cables in-between the individual turbines of the wind farm. The
optimal cable design has been chosen, taking into account both
technical and economic aspects. The final choice fell on
3-conductor, 400 mm2 copper PEX cables for the cables
from the groups to the substation and on 150 mm2 copper
cables for the internal cables between the individual turbines. Only
one 95-mm2 copper cable is connected to the turbine at
the end of each row.
By 25 June 2002 cables have
been connected for 16 turbines and the initial production from this
wind farm is expected to be brought ashore in mid-July 2002. All
turbines are scheduled to be connected by the end of October.
|
|

Cables are submerged by the
cable-laying vessel

The cable submission is scheduled to be
complete by the end of October
|
|
Status: turbine erection
The erection of the turbines is well under way
and Vestas and A2SEA, Vestas' sub-supplier, now work simultaneously on
two turbines from each of the two crane vessels in operation. This
ensures efficient installation work in that each of the vessels is
capable of erecting one turbine each day, weather conditions
permitting.
By June 25 a total of 26 turbines were erected.
As the crane vessels continue erecting turbines,
Vestas' staff are making the final installations inside the already
erected turbines and preparing them for operation. The staff are
transferred to the turbines from the crane vessels by boat.
|

Busy
activities at the Port of Esbjerg, preparing the turbines for departure
on the two crane vessels

By June 25 a total of
26 turbines were erected
|
|
Status: foundations
The
foundation pile driving is on schedule and more than 60 % of the
foundations are installed. By 25 June a total of 49 piles had been
driven into the seabed and transition pieces had been installed on 45
of these. At the current speed of driving and with acceptable weather
conditions, MT Højgaard, the foundation contractor, expects the drive
the last foundation piles in early August.
|
|
|
Weather
forecast programme
Since the
installation work at Horns Rev very much depends on calm weather it is
of utmost importance to be able to make precise weather forecasts. For
this purpose, Tech-wise A/S, which is a subsidiary of Elsam A/S, has
developed a reliable weather forecast programme which is often used by
the partners of the Horns Rev project.
The programme is
based a weather forecast programme developed by the Danish
Meteorological Institute and on a wave forecast model developed by DHI
Water & Environment. Combined with local measurements of actual
wind, wave and current conditions at Horns Rev this programme produces
reliable forecasts for the area at Horns Rev with a 48-hour time frame.
The forecasts are made available to the project's contractors and are
used frequently in connection with the scheduling of tasks.
|

Wind speed forecast

Wave forecast
|
|
Monitoring
of the environment
The environmental monitoring programme at Horns
Rev is according to schedule.
The movements
of the seals in the area is still monitored via satellite. To be able
to register the right position of the seal it must emerge from the sea
for some time and therefore there might be some problems with locating
the seals from time to time.
Birds visiting the area around the Horns Rev
construction site are observed and their whereabouts are presently
being registered from the air.
In autumn 2002 the ornithologists would like to
find out how the birds react to the wind turbines. It is therefore
important for them to be able to estimate and calculation the risk of
collision for the individual kinds of birds. Will migrating seabirds
pass the wind farm while the turbines are in operation? - or do they
prefer to fly by or over the wind farm? And, not least will they be
attracted to the marking (lights) of the turbines during night time?
These are some of the questions which should be answered during
monitoring.
However, these questions are
not answered by performing bird counts. The birds must be visually
observed and therefore, the ornithologists have carried out initial
inspections of the wind farm with a view to finding suitable spots
from where the park can be observed. In late August the first
observations will take place. In spring 2003 radar surveillance
equipment may be installed at the substation so that bird migration
and possible collisions can be monitored from ashore.
|

The movements of two seals during 10 days

Results of the counts of the common scoter (Oidemia
nigra), spring 2002.
Click
here for further details.
|
|
|

The wind farm as seen from Blåvands Huk on 3 June
on which day approximately 15 turbines were erected. Click on the
picture in order to enlarge.
|
| Issued
newsletters
|
|