|
Installation
of turbines in progress
The installation of turbines on the
foundations is now in full progress at the construction site at
Horns Rev. By May 23, a total of seven complete turbines were
installed, including rotor.
A2SEA, a sub-supplier of Vestas', now
has both crane vessels in operation. The crew onboard the Ocean
Hanne continues the installation of tower sections on to the
foundations whereas the crew on Ocean Ady installs the nacelles.
If the weather allows it both vessels
and Vestas' crew are in operation 24 hours a day throughout the week.
Towers and nacelles are pre-installed
at the Port of Esbjerg to minimize the offshore installation work.
Onboard the Ocean Ady, a tailor-made
rack holds two nacelles.
Once the crane vessel is positioned
next to the already installed tower, the nacelle, with two
pre-installed blades, is lifted on to the tower and is bolted to the
top flange. Then the third blade is installed by means of
tailor-made lifting equipment. The lifting process is critical and
requires good weather conditions.
The crane vessel remains next to the
tower during final installation and final tightening of the bolts.
|
|

Pre-assembly
of nacelle at the Port of Esbjerg
.
First
nacelle loaded on to the crane vessel 
Nacelle
almost in position on turbine tower

Preparations
for lifting of third blade

Third
blade installed (photo: Jan Vium)

Complete
turbine
|
|
Status
on foundations
The driving of foundation piles and the
installation of transition pieces are on to schedule. By May 23, 28
piles have been driven of transition pieces have been mounted on 26 of
these. Erosion layers have been established at 22 of the turbines.
|

Buzzard,
the pile driving vessel, at sea
|
|
Cable
pulling within the wind farm
Cable pulling has
been initiated within the wind farm. The first two inter-turbine
cables have been pulled along the seabed and will be trenched soon in
1-2 meters' depth.
The cables between
Eltra's substation and the individual groups of turbines, the
so-called radial cables, are expected to be pulled within the coming
fortnight. The same vessel, the "H.P. Lading" that pulled
Eltra's submarine cable ashore from the substation, trenches these
cables.
|
|
|
Noise
measurements
During the construction of the wind
farm a number of environmental aspects are monitored closely. One of
these aspects is the underwater noise during pile driving. Hence, the
sound pressure is measured during pile driving.
Technicians from Tech-wise's department
for noise and vibrations measure the noise in various depths and at
various distances from the pile driving scene. The measurements are
currently being analysed.
|

Pile
driving
|
|
Eltra's
submarine cable
The work of pulling Eltra's submarine
cable from the substation and ashore is on schedule. Transmission of
power is expected to begin on July 1, 2002. The mentioned submarine
cable now has to be trenched and to be connected to the land cable in
the cable transition station, which is located approx. 1 km from the
coast at Oksby. The land cable from Oksby and to the substation at
Karlsgårde has already been pulled.
Right now, the submarine cable is being
connected to the offshore substation and a number of finishing and
testing jobs are being carried out at the offshore substation.
|
Eltra's
substation
|
|
Owner
coordination
The
Horns Rev project is a big project with a huge number of activities,
numerous business partners, great dependence on good weather
conditions and, last but not least, a very tight time schedule. This
requires very close coordination between all parties involved. For
this Elsam has gathered a team of coordinators at the Port of Esbjerg
who manage the coordination of traffic, diving activities and safety
aspects related to the Horns Rev construction site.
Tech-wise
A/S, one of Elsam's subsidiaries, has been entrusted with handling
all the practical work as Owner's engineers. Before this project,
Tech-wise A/S has managed engineering, coordination and supervision
jobs in connection with numerous other projects.
Traffic
coordination
The
traffic coordination team supervises all project-related sea traffic
to and from the Horns Rev construction site. Traffic coordination is
manned 12 hours a day, seven days a week, and receives information
from all sailing units such as position, activity and number of
persons on the site.
Diving
coordination
As
part of the safety measures for the Horns Rev project, Elsam has
established and operates a pressure chamber. The chamber is located on
board the vessel "Gitte Iversen" which is at anchor just
outside the construction site area. The vessel crew consists of two
men and a person to operate the pressure chamber.
Safety
coordination
The
Owner is in charge of the coordination of safety on the construction
site. This includes the site at the Port of Esbjerg and the offshore
site. The coordination is carried out according to the authorities'
rules and regulations; including requirements made by Arbejdstilsynet
(The National Working Environment Authority) and Søfartsstyrelsen (The
Danish Maritime Authority).
|

Traffic
coordination is manned 12 hours a day, seven days a week

The
vessel "Gitte Iversen" with pressure chamber before departure
from the Port of Esbjerg.
|
|
Web
cam transmissions from the Horns Rev site
You
can now follow the live transmissions from the web-cam
at Horns Rev.
The
web cam has been installed on Eltra's substation and shows turbine no.
91 (see also below map).
The
camera will be moved to a better location soon. This means the camera
will be able to move freely and therefore also cover the areas of the
wind farm where there is most activity.
The
transmission is made by radio link to Elsam's power station in Esbjerg
from where the pictures are transferred to Elsam's Internet server.
|
|
|
Numbering
of turbines
All
turbines in the wind farm have their own number. The sketch shows the
principle of numbering. In the top horizontal row, from the left to
the right, the numbering starts with turbine no. 01, turbine no. 11,
then turbine no. 21 and so on and so forth. In the second horizontal
row from the top, turbines no. 02, 12, 22 etc. are found. The black
square marks Eltra's substation.
|

Large
image
|