|
Read about:
| Overall
time schedule - manufacturing and installation
The Horns Rev project is now taking shape. The
first parts for the project are being manufactured and shortly,
almost all parts for the project will be in production to be in
available and in place on time for the start of installation on
March 4, 2002. The main activities and milestones are shown on the
schedule.
Remote control and monitoring
system
The windfarm at Horns Rev presents new kinds of
problems, which have not been experience earlier in connection with
windfarms - caused especially by the difficult access conditions and
the latest demands for load control set up by Eltra as well as
Elsam's operation department.
The monitoring technologies used are the same as
the ones used for onshore plants in which reliability-centred
maintenance is practised. The control systems of the turbines
regularly collect operating statistics for all essential components
such as gear, generator, yaw system, pumps, etc. Furthermore, all
the turbines are fitted with a state-of-the-art vibration control
system, which monitors main bearings, gear and generator and
reports/sets off an alarm when a measuring point shows sign of
change in the condition of a monitored component. All data are
regularly transmitted to the remote control and monitoring system
from where Elsam's central maintenance system has access to the
data.
Load control
The need for load control requires the same kind
of control of the windfarm's production as a combined heat and power
plant unit. An example could be reducing the production from the
windfarm due to grid limitations and/or participating in a load
control scheme within the limits of actual wind speeds.
This requires a broad band communication system of
a reasonable price, reliability and flexibility to meet future and
yet undefined demands as well as immunity to electrical
interruptions including for instance lightening.
These various requirements have resulted in a
solution based on fibre optics and Internet technology based on TCP/IP
protocol. The turbines are placed in ten circles of eight turbines
each, which are connected in a 100 Mb Ethernet of fibre optics in
the high-voltage cables which again connect the turbines to the
substation.
The signals from the substation will be
transmitted via the fibre optic cables in the 150 kV submarine cable
or, alternatively, via an radio signal chain to Esbjergværket where
all data are collected and where the day-to-day control and
monitoring of the windfarm will take place.
|
|

Overall time schedule
Picture
in large format
|
|
Remote control system
Picture
in large format |
|
|
| Status:
Driving of foundation piles for Eltra's substation
On October 22, 2001 the Rambiz returned to Esbjerg
Harbour from Horns Rev in search for shelter after a week of changing
weather and wave conditions. It had not succeeded in driving the three
large M-piles for the substation. In stead, time had been spent on
mounting the boat landing arrangement (welded construction, work not
finished yet.) and on driving the large pile for the J-tube for the
submarine cable to the shore.
As described earlier in our October newsletter, the
movements of the ship caused by waves are amplified in the 85-m high
crane boom. This means that the driving of piles, which is a job
requiring immense precision, was not possible and with a weather
forecast not promising improvements in the weather, the Rambiz had to
return to Esbjerg.
The boat landing arrangement has later been
reinforced to withstand winter storms by the help of the boat Naomi B.
The tripod construction for the turbine cables have
been installed and the three piles have been driven including test
pile A1, which was to be monitored during the driving session. The
tripod construction has not been grouted yet but preliminary
calculations made by Dutch HBG do not cause any concern about damage
occurring during a possible storm. The grouting will commence as soon
as possible to have sufficient settling temperatures.
It turned out that the Rambiz had to stay in Esbjerg
Harbour longer than expected and worries emerged as to whether the
outstanding tasks could be finished before winter set in. It is
therefore of utmost importance that the necessary measures are taken
as soon as possible to minimise the risks. On November 15, 2001 HBG
decided to remove equipment from the barge and transfer the barge to a
fortnight's job in Belgium.
Since the placement of the three piles is crucial to
the design and construction of the support bearings of the substation,
it is of utmost importance that phase 1 is completed as
soon as possible. The constructor is currently evaluating the various
possibilities of driving the three piles with sufficient precision and
independently of wave impact. A decision is expected very soon.
|
Rambiz at Esbjerg Harbour

Wave heights at Horns Rev (30 days)
Picture
in large format |
| The
Horns Rev prototype for Tjæreborg almost ready
Vestas has completed the manufacturing of the tower
and blades for the prototype turbine scheduled for erection in
Tjæreborg on December 5, 2001. The finishing of the nacelle is
currently made at Vestas' production facilities in Ringkøbing,
Denmark.
The design of the new turbine to be erected in
Tjæreborg is almost an exact copy of the design of the eighty
turbines to be erected at Horns Rev in 2002. A heli-platform will be
fitted on top of the turbine's nacelle for hoisting fitters on to the
turbine from a helicopter, for testing the installation of the turbine
marking on the nacelle's roof and for various advanced controls. The
erection of the prototype thus provides numerous opportunities for
testing the turbine thoroughly before the erection at Horns Rev.
Prototype data:
| Type: |
Vestas V80 - 2MW |
| Power output: |
2.000 kW |
| Hub height: |
60 m |
| Rotor width: |
80 m |
| Weight excluding
foundation: |
258 tonnes |
| Expected annual
electricity production: |
approx. 5,500,000 kWh |
|

The foundation for the new turbine was cast on November 8, 2001.
Grouting required before turbine erection

Tower sections

High-voltage unit to be installed in the tower bottom
|
| Exhibition
at Denmark's most Western Point, Blåvandshuk
In connection
with the construction of the World's so far largest offshore windfarm
at Horns Rev in the North Sea Elsam, Eltra (grid operator), Vestas
(turbine producer), the county of Blåvandshuk and the business and
tourist board of Blåvandshuk have opened a permanent dynamic
exhibition about the entire project.
The exhibition has been arranged at
Blåvandshuk, Denmark's most western point, in the existing house of
the lighthouse keeper. In a way, the exhibition will become the
closest neighbour to the windfarm during its construction in the
summer of 2002. The distance between the lighthouse and the windfarm
will be approx. 14 km.
The opening hours of the exhibition are
10 a.m. through 3 p.m. every day, except for December 24 and 25,
December 31 and January 1. Free entry.
You'll find the exhibition at:
Blåvand Tourist Information/Blåvand
Lighthouse
Fyrvej 106
6857 Blåvand
Phone: +45 7527 5411
Directions:
Visualisation of the windfarm from the
Blåvand Lighthouse. Click
here.
Exhibition languages: Danish
and German.
|


|
| Birds
gone astray - follow-up to the October Newsletter
Once again nature has shown us its great forces
offshore in the North Sea. This time, a small songbird called the
thrush is the victim of nature's great forces.
In connection with the pile driving for the
substation a strange phenomenon was discovered in last September. The
Rambiz and other vessels were suddenly invaded by "tame"
songbirds, which flocked around the vessels and landed on decks,
inside the wheelhouse, on the shoulders and heads of the workers,
anywhere possible. But a closer look revealed that the birds were not
tame. They were exhausted and were looking for a place to rest. Some
of the birds were so exhausted that they literally dropped dead on the
decks while others continued after a short rest. The workers had to
brush the birds off the decks in able to work.
What had happened?
During autumn, thousands of songbirds migrate along
the west coast of Jutland. Sometimes the easterly winds are so strong
that the birds are forced away from their normal migration route. This
happened at exactly the same time as the construction work at Horns
Rev and some birds were forced to cross over the Horns Rev where the
vessels became their only steady ground.
The observation of such phenomena is an important
piece of the puzzle of describing how it is was before the erection of
the turbines. Once the turbines have been erected in 2002, this very
same phenomenon may occur.
|
Small songbirds such as these photographed on the Rambiz are likely
to land on the turbines in rough weather. These birds may be so
exhausted that they literally drop dead. Others again may be so
exhausted that they collide with the turbines. Many birds, on the
other hand, may also find a safe haven and a place to rest and to
restore their energy so that they will become able to manage the last
part of their migration.
|
|
Link to DMI's (Danish
Meteorological Institute) wind speed and waves forecast
The weather plays an important role in connection
with implementing the planned activities at Horns Rev. You can follow
the weather conditions in the North Sea by visiting the homepage of
DMI giving forecasts of:
|
DMI wave height
forecast (example)
|
| Preparation
of auxiliary equipment for the substation
In connection with the construction of the Horns Rev
windfarm Elsam will install various auxiliary equipment on the
substation such as: 34 kV switchgear, house load transformer, shunt
reactor and a 1,000 kW diesel generator. These components will be
installed at Eltra's Horns Rev substation and should therefore be
ready for supply by December 22, 2001.
The diesel generator is needed for Horns Rev in
order to establish an auxiliary supply of electricity to the
substation as well as to the turbines. It is also required for
maintaining navigation and marking of turbines and for keeping the
various systems warm and dry in case the connection to the shore is
cut off for a long period of time. The capacity of the diesel
generator corresponds to the consumption of approx. 2,000 standard
households.
Installation in containers
The distributor and the diesel generator are
installed in containers, which are designed according to offshore
standards. This means they are able to withstand the loads which they
are subjected to during offshore transportation. In case of
considerable damage, the entire container may be taken off the
substation and taken ashore for repair. Preparations have been made
for this and in that connection lifting of the containers has been
tested. The tests included loading the containers with 2.5 times
standard load. Since the containers were not large enough physically
to hold 50 tonnes (e.g. the distributor) four leads of 7.5 tonnes each
were attached to the containers during the lifting tests.
|

The container is loaded with concrete blocks

The container is ready for being lifted
|
| Issued
newsletters |
|
|