Newsletter on the Horns Rev Project
    

 
- November 2002 

            

Læs om:

 

Commissioning in progress

The commissioning of the 80 wind turbines in the wind farm is in progress. At present (November 5, 2002) 30 wind turbines have been commissioned and 13 are under start-up. The commissioning is 3-4 weeks behind schedule.

Vestas has increased the number of commissioning teams and transport boats, and the two previous crane vessels permanently function as floating hotels in the wind farm area. Furthermore, nightwork is performed under tight rules.

These initiatives mean that all the wind turbines will be commissioned by Christmas 2002.

 

 

 

 


30 wind turbines have been commissioned and are ready to produce electricity
(November 5, 2002).


Horns Rev – 80 wind turbines – 160 MW.

Damage to the 2 MW offshore wind turbine in Tjæreborg

At approx. 9.00 a.m. on Monday November 4 the new 2 MW offshore wind turbine in Tjæreborg was damaged. The wind turbine is a prototype of the 80 wind turbines, which Elsam has erected at Horns Rev. Eye witnesses recount that the wind turbine exceeded the maximum allowable numbers of rotation whereupon the blades collapsed. The wind speed at that time did not exceed 10 m/s. The wind turbine has not yet been finally taken over by Elsam. Already on Monday engineers from Vestas started investigating the reason for the damage and to find out whether the fault can also occur on the Horns Rev wind turbines.

See press release from Vestas

 



The wind turbine exceeded the maximum allowable numbers of rotation whereupon the blades collapsed .

Helicopter transport

Elsam has entered into an agreement with Uni-Fly A/S on helicopter transport to the offshore wind turbines at Horns Rev. Uni-Fly A/S is to transport service engineers to the wind farm in connection with service and inspection.

The helicopter to be used for this transport, has just arrived at Esbjerg Airport, where Uni-fly marked the occasion with an open house arrangement.

The helicopter is to transport service engineers to the wind turbines where they are hoisted down onto the platform placed on the wind turbine roof. Subsequently, the service engineers are hoisted from the platform like when rescue helicopters pick up people in distress. This method is widely used abroad, where, among other things in the channel area, shipping pilots are moved from vessel to vessel by helihoist.

 


Hoist training at Elsam's 2 MW offshore wind turbine in Tjæreborg.

New offshore foundation type used in Frederikshavn

On Wednesday October 30 the new patent pending foundation type “bucket foundation” was used for the first time in full scale. The foundation is to carry Denmark’s largest wind turbine so far, which is one of the four 125 m high offshore wind turbines to be erected off the harbour of Frederikshavn.

The 135 tonnes foundation has the shape of an upturned bucket, which is sucked into the sea bed by means of vacuum. The bucket foundation developed in Denmark is patent pending and has large prospects, as it makes manufacture, handling and erection less expensive and subsequent make removal of foundations in connection with offshore wind turbines easier.

The company MBD Offshore Power A/S – a development company with Novasion aps, Ørskov Staalskibsværft A/S, Bladt Industries A/S, MarCon A/S and Elsam A/S as shareholders – has been in charge of the commercial development of MarCon’s patent. The foundation has been developed in a close and formalized co-operation with Aalborg University Centre.

The wind turbine to be placed on the new foundation type is Denmark’s largest – a 3 MW Vestas wind turbine. The wind turbine is expected to be placed on the foundation in week 49 and is to be in operation by the end of 2002. For time reasons the remaining three wind turbines are placed on traditional foundations and are expected to be put into operation by June 2003.

 


The 135 tonnes foundation has the shape of an upturned bucket.


The foundation is to carry Denmark’s
 largest wind turbine so far.

Clean-up on site

As part of the clean-up after the on-site works at Horns Rev, the compression chamber was removed from the transformer platform. The compression chamber was placed on the platform as a safety measure in connection with the numerous diving operations performed in connection with the construction of the offshore wind farm.

 


The compression chamber is removed from the transformer platform. 

Issued newsletters

 

 

Elsam A/S
Overgade 45
DK-7000 Fredericia
Phone: +45 76222000
Fax: +45 76221962
www.elsam.com