| Status:
Driving of Foundation piles for Eltra's
Substation
The driving work at Horns Rev were
planned to start on September 2, 2001 but only few days before the
barge crane, the Rambiz, should have departed from Rotterdam for the
Reef, a strong low pressure was reported in the North Sea and the
crane arrived with a fortnight's delay.
Phase 1 activities related to the
pile driving:
- Positioning and installation of a
pile driving "mould" on the seabed.
This mould consists of a number of
welded steel profiles holding thirteen pile sleeves in position
and supporting the J-tubes (tubes for 36 kV and 170 kV cables) to
secure the individual position of the piles in relation to each
other once the mould and J-tubes have been placed correctly.
The Rambiz is held in position by
means of four anchors placed diagonally at maximum 350 metres'
distance. During pile driving its position is changed by pulling/releasing
the anchor chains.
- Erosion protection. As erosion
protection, a 1-metre thick stone mattress is placed around the
pile. The mattress consists of a filtration layer of granite
stones at the bottom and at the top, a reinforcement layer of
large granite stones. This is done by the stone dumping vessel
HAM 601 (owned by the Dutch HBG).
- Pile driving through the pile
sleeves by the Rambiz.
- Establishment of the boat landing
arrangement as well as diving activities in connection with the
fitting of the J-tubes.
Overall Status as of October 22, 2001
All secondary piles for the
substation structure have been driven. Pump wells, tripod piles for
the 36 kV cables (including test pile in full depth for pile driving
tests) as well as pile for 170 kV J-tube.
The three large piles for the
substation foundation and six collision piles have not yet been
driven.
Handling and driving of the first
piles have been done be means of the crawler crane placed on the
Rambiz' front deck between the main crane booms.
The piles for the substation
foundation must be driven by the crane's main boom due to their
size. This has produced new challenges because even small movements
of the barge are amplified in the top of the boom causing the load (pipes, vibrators or pile driver)
to move sideways, movements
which cannot be compensated. As the piles are fixed at the pipe
sleeved on the seabed it is very difficult to control the pile
during driving since the top of the pile moves with the vessel's
movements.
These movements also
endanger the work of the diver who tries to guide the pile into the
sleeve, which is made even more difficult as the visibility is
typically approx. 0.5-1 metre and the currents are strong.
A driving sequence has more lifting
operations:
- Lifting of the pile by two cranes
(the Rambiz and the crawler crane) by which the pile is turned
while in the air
- Dismantling of the lifting device
and positioning of driving head including vibrating to approx.
12 metres' depth
- Replacement of vibration by
55-tonnes hydraulic pile driver. Driving until specified level
has been reached
The driving has been put on hold from
October 20 2001 due to weather conditions (wind and waves) and defect
driving-equipment has delayed the driving processes. In the meantime,
other installations are made which are less dependent on weather
conditions. It is to the credit of the staff who works almost around
the clock to finish the work as planned - it is not unusual for them
to work 16-18 hours a day.
With the present weather forecasts of
increasing wind speeds and change of wind direction from east to
west, the driving of piles may continue into the month of November.
Latest news: The Rambiz with staff is
currently demobilising and heading towards Esbjerg Harbour.
Bird
Migration in the Area
Large swarms of songbirds have found
interest in following the construction work in connection with the
driving of piles for Eltra's substation. These small birds are
migrating along the west coast of Jutland. The migration route
depends on the wind direction and in the days of easterly winds -
which was when the pile driving took place - the birds came to the
area. Many birds were exhausted and took a rest on the Rambiz and
other vessels.
The workers were actually able to
pick up the birds with their bare hands where they would heat
themselves. To make the birds fly the workers had to push the birds
into the air. Many birds died of exhaustion but others continued
after having regained their strength. This is important information
in relation to the environmental aspects during construction of the
windfarm. Once the turbines have been erected, this may happen
naturally again - songbirds lying dead around the turbines. The
deaths of these migrating birds are therefore not the result of the
operation of the turbines themselves.
|