Commissioning
of turbines in full progress
Vestas and its
sub-suppliers succeeded in finishing the turbine installation work two
weeks ahead of schedule and now the activities revolve around making
the final preparations for the commissioning of the turbines. At
present Vestas employs 30 electricians and commissioning specialists
at Horns Rev and the two crane vessels now act as hotel ships for
Vestas' staff.
The electricians are
sailed from turbine to turbine to finish the internal cable work
inside the turbines. Following the electricians are the commissioning
specialists who then execute thorough testing procedures to prepare
the turbines for actual power production.
Elsam's staff is
careful to be well ahead of Vestas' staff. It
is the task of Elsam's
staff to test the cables and connect the cables to the grid
of the wind farm.
As of October 8,
2002 twenty turbines have been commissioned and are ready for power
production.
Several teams are
testing and commissioning the farm's remote monitoring and control
system. The communication system has already been commissioned from
ashore and to Eltra's substation. The connections are now made between
the individual turbines and the substation via fibre optic cables in
the farm's high-tension cables.
All 80 turbines of
the farm should be commissioned by mid-November depending on the
near-future weather conditions.
|